Data Network Upgrade St Andrews Aged Care Byron Bay

This was 100k dollar data network install job to refit Byron Bay Site, after St Andrews took over from Ferros Care, for Club IT.

The project took 3 months to complete and involved a leading hand and 2 electricians onsite.

Works included.

Removal of existing obsolete data network.

Install of Cat 6 structured network.

Install of IP security cameras.

Install of new data racks in resident buildings.

Install of fibre optic back bone between racks.

Install of cabling for new nurse call system.

Project had to be completed with residents onsite and minimal downtime during cutovers.

Project was completed in under required timeframe.