This was 650k dollar electrical job to refit Living School after the 2022 floods, with Balanced Earth Constructions being the principle building contractor
The project took 4 months to complete and involved a leading hand and 2 electricians onsite.
Works included.
Demolition and removal of existing electrical and data cabling and equipment that was flood affected.
Install of temporary campus electrical and data at Skennars Head site
Electrical refit of school, canteen, house and keeps building.
Replacement and upgrade of data networks.
Sourcing and install of specialty spectrum changing LED lighting.